
Cummins says Royal Columbian Hospital needed reliable power for critical and often life-saving care in every circumstance. Fraser Health had two 3,250 kW QSK-95L generator sets, paralleling controls, switchgear, transfer switches and a master control system. Together, the engines offered 6.5 megawatts of installed capacity and were ready to accept the required facility load in under ten seconds. On the brochure, every lamp was green and the customer was “Always On”.
The Royal Columbian Hospital power outage of 19 December 2020 then sent vital circuits in the health care centre and emergency department into darkness. A source familiar with the incident told theBreaker that a neurosurgical procedure was completed using headlamps, electrically operated doors could not be opened and access to medication was disrupted. Fraser Health said the emergency generators did not activate because power to the wider hospital campus had not been lost. There is the whole absurdity in one electrical diagram: 6.5 megawatts waiting patiently for the correct sort of darkness while clinicians dealt with the wrong fucking kind.
Six And A Half Megawatts Of Confidence
Royal Columbian is not a site where standby power is decorative. Cummins described it as Fraser Health’s busiest hospital and the only one in British Columbia combining cardiac care, trauma, neurosciences, high-risk maternity and neonatal intensive care on one campus. It was also designated to serve as a post-disaster health care facility. When electricity disappears in a place like that, the problem stops belonging to the facilities department very quickly.
Cummins understood the stakes perfectly when it wrote the sales copy. The company said its two QSK-95L sets would provide dependable power, accept the required hospital load in under ten seconds and support the transition to a post-disaster facility. Its supply extended beyond the engines to PowerCommand 3.3 paralleling controls, IEM switchgear, ASCO transfer switches and a master control system. This was not a pair of diesel lumps abandoned beside a loading bay with a handwritten note saying good luck. It was presented as an integrated answer to a clinical requirement where failure could become catastrophic before some poor bastard had finished reading the alarm panel.
The case study adds another layer of corporate confidence. Cummins said the equipment used its “Power of One” capability, with key systems designed and manufactured in-house to deliver efficiency and “unparalleled reliability”. It praised the generators’ ability to accept 100 per cent of nameplate-rated load in a single step and concluded that Cummins keeps health care customers continuously powered. Those are magnificently absolute claims. They deserve to be tested against the decidedly less absolute electricity that reached the hospital’s operating rooms.
The Hospital Stayed On And Went Dark
According to theBreaker’s report, two intensive care patients were in operating rooms when the lights went out. One patient was moved from a darkened theatre to another operating room, while a neurosurgical procedure was completed using headlamps. The source also said electrified doors could not be opened and an Omnicell automated medication cabinet was temporarily unavailable. Ten admitted patients in the emergency department were transferred to unaffected areas.
The medication problem also appeared in a pharmacy downtime memo quoted by the report. It said the outage had affected access to Omnicell cabinets and that there had been confusion over how staff should obtain medicines during the interruption. No patients were reported harmed, which matters enormously, but it does not turn the event into a reassuring little systems test. Staff moving patients, finding light and working around locked equipment is human mitigation. Calling that a technical success would be industrial-strength bollocks.
Fraser Health said the outage lasted less than an hour and followed a circuit-breaker failure associated with ongoing redevelopment work. Its spokesperson said the failure affected vital circuits within the health care centre and emergency department while power remained available elsewhere in the building and across the campus. The failed breaker was replaced. So far, this is already a grim account of a localised electrical failure in precisely the rooms where “localised” is not a comforting word.
The Generators Did Exactly Fuck-All
Fraser Health’s explanation for the silent generators was beautifully technical and completely useless to anyone standing in the dark: they did not come online because there had been no loss of power to the hospital campus itself. The campus still had electricity, therefore the emergency condition that would call on the generators had not occurred. Vital clinical circuits had failed, but the wider supply remained live. The hospital was powered and unpowered at the same time, depending on whether you were reading a system state or trying to finish neurosurgery.
That explanation makes the outcome worse, not better. It describes a gap between available generating capacity and usable electricity, large enough for an operating room to fall through. The engines could be ready to take load in under ten seconds, but readiness meant bugger all if the event did not produce the signal that summoned them. Capacity sat on one side of the arrangement; clinicians with headlamps stood on the other. Somewhere between them, the promised resilience became an expensive spectator.
This is why raw megawatts make such seductive marketing. A large number looks reassuring because it answers the easiest question: how much power can the generators produce? The nastier question is whether that power reaches the right circuits under the failures that actually occur. On Fraser Health’s own account, a breaker could fail, vital circuits could go dark and the wider campus could remain sufficiently energised to leave emergency generation out of the response. Six and a half megawatts is impressive engineering. Six and a half megawatts that nobody calls is just a very costly piece of scenery.
Twenty-Five Shutdowns To Build A Safety Net
The electrical work was not minor. Glenco Electric says the Phase One project involved $28 million of electrical design and construction, including a new energy centre intended to serve the 75-bed Mental Health and Substance Use Wellness Centre and the existing Royal Columbian campus. The work included 25 shutdowns in one month to cut the operating hospital over to the new installation. Glenco dates project completion to March 2020, while Fraser Health says Phase One opened that year and its new energy centre replaced the ageing power plant and prepared the hospital for growth.
Cummins likewise described a complex design-and-build job carried out around a fully operational hospital. Its sales and service groups worked with engineers, contractors, consultants and Fraser Health facilities management, it said, to establish requirements, ensure compatibility and confirm functionality before installation. Meetings were held to make sure the design criteria were met. The case study does not present Cummins as a remote engine vendor with no view beyond the crankcase; it presents a team embedded in the system-level work and congratulates everyone involved for creating a complete and highly reliable installation.
That makes the central question unavoidable. When the design teams considered emergency operation, what was supposed to happen if a vital clinical circuit failed while the rest of the campus supply stayed alive? A post-disaster hospital does not get to choose only neat disasters that arrive through the approved entrance and trip every expected sensor. Real failures are awkward, partial, grubby things. They break one component, preserve another and expose whatever assumptions have been hiding inside the logic. If the safety net only opens for a total campus outage, the smaller hole can still swallow an operating theatre.
The Brochure’s Timing Is Exquisite
Cummins printed its Royal Columbian case study in December 2020, the same month as the outage. The document may as well have arrived with every status light glowing. It praised superior uptime, prompt problem-solving, strong relationships and unparalleled reliability, before signing off with “Always On”. Meanwhile, the reported reality from 19 December involved dark operating rooms, an inaccessible medication cabinet and staff finishing neurosurgery with lamps strapped to their heads. Corporate timing does occasionally achieve a kind of obscene perfection.
The point of a case study is selection. The supplier chooses the capacity, the response time, the engineering collaboration and the flattering photograph; all the messy operational texture gets cropped out. Cummins’s version ends when the equipment has been installed and the relationship has been praised. Customer Corner simply lets the film run a little longer, until the new electrical environment encounters a failed breaker and all that polished certainty starts throwing sparks.
Cummins still hosts the story as “Reliable backup power for Canada’s healthcare system”. That title survives because the engines and associated equipment were installed, because the project was complicated and because the brochure can document what the equipment was designed to do. Yet a backup-power success story that omits the Royal Columbian Hospital power outage, when vital circuits went dark and the emergency generators did not start, is missing the most revealing page. You cannot market resilience only up to the moment some inconvenient shit actually happens.
No Patients Harmed Is Not A Victory Lap
The report says no patient was harmed, and that is the best fact in this entire story. It belongs first to the people who managed the failure: the clinicians who continued a procedure under headlamps, moved an ICU patient, transferred emergency patients and navigated temporary medication disruption. Their response prevented a frightening incident from becoming something much worse. It does not retroactively illuminate the room or make the idle generators part of the rescue.
Institutions love “no harm” because it can be polished into the shape of reassurance. In safety-critical work, however, escaping harm is not the same as demonstrating that every safeguard performed as intended. Sometimes the professionals at the sharp end catch what the infrastructure drops. Treating their recovery work as proof that the system coped is a shabby bit of arse-covering, particularly when the system had been sold as suitable for every circumstance.
Fraser Health replaced the failed circuit breaker and said an internal investigation had identified the redevelopment-related cause. What its public explanation also preserved was the brutal mismatch at the heart of the incident: the outage was serious enough to affect vital clinical circuits, but not broad enough to start the emergency generators. That is not a footnote to the power story. It is the power story.
Customer Corner’s Discharge Note
Fraser Health now describes the 2020 energy centre as infrastructure that replaced the hospital’s ageing power plant and supports its continuing expansion. Cummins continues to offer Royal Columbian as evidence of reliable health care backup. The redevelopment has moved forward, the hospital has grown and the marketing language remains available for the next customer who wants to feel protected by a large number followed by “MW”. Customer Corner is here to provide the less soothing unit of measurement: what happened in the room.
On 19 December 2020, the campus had power. Vital circuits did not. The hospital had 6.5 megawatts of Cummins generating capacity, yet Fraser Health said its emergency generators stayed offline because the campus-wide trigger condition had not been met. A source familiar with the incident said neurosurgery continued by headlamp. No amount of brochure wank can reconnect those facts into a success story.
Cummins can keep “Always On” glowing at the bottom of its case study. Fraser Health can keep its explanation for why a powered campus contained dark clinical rooms. Customer Corner will keep the other status light visible: six and a half megawatts installed, vital circuits dark, surgery by headlamp. That is the customer case study the glossy bastards forgot to print.
Lee Thompson – Founder, The Cummins Accountability Project
Sources
- Cummins – Royal Columbian Hospital case study: Reliable backup power for Canada’s healthcare system
- Cummins – Original Royal Columbian Hospital case-study PDF, bulletin 5676429, December 2020
- theBreaker – Royal Columbian Hospital power outage worse than reported, 30 December 2020
- Glenco Electric – Royal Columbian Hospital redevelopment, Phase One electrical project
- Journal of Commerce – First phase of Royal Columbian Hospital redevelopment completed, 29 May 2020
- Fraser Health – Royal Columbian Hospital redevelopment project overview, May 2026
